UGC NET LAW (058) · UNIT 08 · MODULE 2: ENVIRONMENT LAW IN INDIA · TOPIC 4

Environmental Impact Assessment and Control of Hazardous Waste in India

How EIA works under the 2006 Notification, how courts have treated it, and the rules that govern hazardous waste and chemical safety.

  • 7 sub-topics
  • 3-point Memory Capsule
  • 9 min read
  • Topic 4 of 10

What this topic covers

7 sub-topics, in the order to study them. Tap one to jump to it.

  1. §OverviewEnvironmental Impact Assessment (EIA) is the preventive tool of environmental law: it asks, before a project starts, what it will do to air, water, land, ecology and people…
  2. 4.1EIA: concept and originCovers Definition, Origin, India, Objectives.
    • Definition
    • Origin
    • India
    • 27 January 1994
    • Objectives
  3. 4.2The EIA Notification 2006: structureProjects.
    • Projects
    • Categories
    • Screening
    • Scoping
    • Public consultation
  4. 4.3Related tools and conceptsCovers Strategic Environmental Assessment, Eco-Sensitive Zones, Forest clearance.
    • Cumulative impact assessment
    • Social Impact Assessment
    • Environmental audit
    • Carrying capacity studies
    • Eco-Sensitive Zones
  5. 4.4EIA: judicial approach and controversiesCovers Recent changes.
    • Recent changes
  6. 4.5Hazardous waste: concept and frameworkCovers Hazardous waste, Legal chain, Key features of the 2016 Rules, Recent amendments.
    • Hazardous waste
    • Schedule I
    • Schedule II
    • Schedule III
    • Schedule IV
  7. 4.6Other waste and chemical safety regimesInstrument Key points Manufacture, Storage and Import of Hazardous Chemical Rules 1989 Regulate major accident hazard installations; require safety reports, on-site…
  8. 4.7Cases on hazardous waste and pollutionBhopal Gas Leak Disaster (1984) and the litigation that followed ( Union Carbide Corp. v. Union of India , 1989; Charan Lal Sahu , 1990) led to the EPA, the Public Liability…
  9. ★Memory CapsuleThe names, dates and one-line facts from this topic, for daily recall.

Revision mode hides the full explanations and keeps each section's key terms, lists and tables and the Memory Capsule. Use it from your second read onward.

§Overview#

Environmental Impact Assessment (EIA) is the preventive tool of environmental law: it asks, before a project starts, what it will do to air, water, land, ecology and people, and whether the harm can be avoided or reduced. Hazardous waste control is the corrective and regulatory side: it governs how dangerous wastes are generated, stored, moved, treated and disposed of, from “cradle to grave”. Both are made under the Environment (Protection) Act 1986, so they are delegated legislation (a notification and a set of rules), not Acts of Parliament.

Back to topic map ↑

4.1EIA: concept and origin#

In brief

Covers Definition, Origin, India, Objectives.

  • Definition
  • Origin
  • India
  • 27 January 1994
  • Objectives
  • Definition. A systematic process to identify, predict, evaluate and mitigate the biophysical, social and other relevant effects of proposed projects before major decisions are taken and commitments made.

  • Origin. The U.S. National Environmental Policy Act 1969 was the first law to require EIA. Rio Declaration Principle 17 asks States to undertake EIA for proposed activities likely to have a significant adverse impact. The ICJ in Pulp Mills (2010) treated EIA as a requirement of general international law for activities with significant transboundary effects.

  • India. Environmental appraisal began in 1976–77 with river valley projects. The EIA Notification of 27 January 1994 under s.3 EPA and Rule 5(3)(d) of the Environment (Protection) Rules 1986 made prior environmental clearance (EC) mandatory for listed projects. It was replaced by the EIA Notification 2006 (S.O. 1533(E), 14 September 2006), which is the operative regime, as amended many times. A draft EIA Notification 2020 was widely criticised and has not replaced the 2006 Notification.

  • Objectives: prevention, informed decision-making, public participation, sustainable development, and a record of project commitments (conditions).

Back to topic map ↑

4.2The EIA Notification 2006: structure#

In brief

Projects.

  • Projects
  • Categories
  • Screening
  • Scoping
  • Public consultation
  • Appraisal and decision
  • After clearance
  • Contents of an EIA report

Projects. The Schedule lists projects (39 items in eight broad groups, for example mining, power, primary processing, manufacturing, services, physical infrastructure, building and construction) that need prior EC. Each item has thresholds by size or capacity.

Categories.

Category Appraised by EC granted by
A (large impacts) Expert Appraisal Committee (EAC) at the Centre MoEFCC (Central Government)
B (smaller) State Expert Appraisal Committee (SEAC) State Environment Impact Assessment Authority (SEIAA)
B1 (within B) Needs a full EIA report and public consultation
B2 (within B) No EIA report or public hearing required

Category B projects are classified as B1 or B2 at the screening stage, and a project located in a critically polluted area or an ecologically sensitive zone may be treated differently under the general conditions of the Notification.

The four stages of the EC process.

  1. Screening (only for Category B projects): decides whether an EIA is needed (B1) or not (B2).

  2. Scoping: the EAC/SEAC determines comprehensive Terms of Reference (ToR) for the EIA study, on the basis of Form 1 and a pre-feasibility report.

  3. Public consultation: a public hearing near the site (organised by the State Pollution Control Board) and written responses from people likely to be affected. Certain categories are exempt, such as the modernisation of irrigation projects and expansion of highways under specified limits, and projects in industrial estates (see the Notification).

  4. Appraisal and decision: the EAC/SEAC examines the EIA report and public consultation record and recommends grant or rejection; the regulatory authority decides, normally by accepting the recommendation. The prescribed timeline is about 105 days in total (60 days for appraisal, 45 days for the decision).

  • After clearance: the project proponent must submit compliance reports on conditions (half-yearly), and the authority can monitor and revoke. EC validity differs by project type, with longer periods for mining and river valley projects, and has been extended in later amendments; check the current text.

  • Contents of an EIA report: project description, baseline environmental data, prediction and evaluation of impacts, analysis of alternatives, Environmental Management Plan (EMP), environmental monitoring plan, risk assessment, disaster management plan, cost-benefit analysis, and summary.

Back to topic map ↑

4.3Related tools and concepts#

In brief

Covers Strategic Environmental Assessment, Eco-Sensitive Zones, Forest clearance.

  • Cumulative impact assessment
  • Social Impact Assessment
  • Environmental audit
  • Carrying capacity studies
  • Eco-Sensitive Zones
  • critically polluted areas
  • Forest clearance
  • wildlife clearance
  • Strategic Environmental Assessment (policies, plans and programmes) versus project EIA; Cumulative impact assessment; Social Impact Assessment under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013; Environmental audit; Carrying capacity studies.

  • Coastal Regulation Zone (CRZ) Notification 2019 (under the EPA) regulates activity along coastlines (CRZ-I to IV) and requires clearance for permitted projects.

  • Eco-Sensitive Zones around protected areas are notified under the EPA; critically polluted areas and the Comprehensive Environmental Pollution Index are used to restrict new industries.

  • Forest clearance (under the Van Adhiniyam 1980) and wildlife clearance run alongside EC; the EC is an additional, not a substitute, requirement.

Back to topic map ↑

4.4EIA: judicial approach and controversies#

In brief

Covers Recent changes.

  • Recent changes
  • Lafarge Umiam Mining v. Union of India (2011): environmental clearances must be given on the basis of sustainable development, precaution and intergenerational equity; courts accept a role for expert bodies and for independent regulators.

  • Utkarsh Mandal v. Union of India (2009, Delhi High Court) on the public-notice requirement for amendments to the Notification.

  • Hanuman Laxman Aroskar v. Union of India (2019): EIA is not a formality; the Court held that the committee must examine cumulative impact and quashed a clearance for the Mopa airport (Goa) for want of proper appraisal and sent it back.

  • Common Cause v. Union of India (2017) and Alembic Pharmaceuticals v. Rohit Prajapati (2020): ex post facto (retrospective) clearance is incompatible with the precautionary principle, save in exceptional cases.

  • Vanashakti v. Union of India (May 2025) struck down the 2017 notification and 2021 office memorandum on ex post facto clearances; a three-judge bench recalled the judgment on 18 November 2025 by a 2:1 majority (Justice Bhuyan dissenting) and asked that the matter be heard afresh. The position remains under consideration.

  • Recent changes: a January 2025 notification exempted industrial sheds, educational institutions and hostels from EC up to a built-up area of 1,50,000 square metres (examined by the Supreme Court in 2025); late 2025 proposals sought to exempt common effluent treatment plants and common municipal solid-waste facilities; the Jan Vishwas reforms changed penalties for non-compliance. Treat all of these as developing law.

Back to topic map ↑

4.5Hazardous waste: concept and framework#

In brief

Covers Hazardous waste, Legal chain, Key features of the 2016 Rules, Recent amendments.

  • Hazardous waste
  • Schedule I
  • Schedule II
  • Schedule III
  • Schedule IV
  • Legal chain
  • Key features of the 2016 Rules
  • occupier
  • Hazardous waste (Rule 3 of the 2016 Rules): any waste which, by reason of its physical, chemical, reactive, toxic, flammable, explosive or corrosive characteristics, causes danger or is likely to cause danger to health or environment, whether alone or in contact with other wastes or substances. It includes wastes from processes listed in Schedule I, wastes containing constituents in Schedule II above prescribed concentration limits, and wastes in Schedule III (Parts A and B, relating to Basel Convention lists). Schedule IV lists “other wastes” such as waste tyres, paper waste, metal scrap and used electronic items.

  • Legal chain: Hazardous Wastes (Management and Handling) Rules 1989 → 2003 amendment → Hazardous Wastes (Management, Handling and Transboundary Movement) Rules 2008 → Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016 (HOWM Rules, in force 4 April 2016, replaced the 2008 Rules).

  • Key features of the 2016 Rules: emphasis on waste minimisation, reuse, recycling and recovery before disposal; the occupier (generator) is responsible for safe storage, packaging, labelling and disposal; authorisation from the SPCB is required for generating, handling and disposing of waste; the manifest system tracks waste from generation to disposal; storage limited to a period not exceeding 90 days (reflected in the 2024 amendment); import of hazardous waste for disposal is prohibited; import for recycling or reuse requires permission from the Ministry; Prior Informed Consent applies to transboundary movement, in line with the Basel Convention; the CPCB and SPCBs maintain inventories and develop guidelines; treatment, storage and disposal facilities (TSDFs) must meet standards; Extended Producer Responsibility (EPR) applies to waste tyres and used oil.

  • Recent amendments: the 2024 Amendment Rules revised EPR deadlines for waste tyres and used oil, set price limits for EPR certificates and permitted import of certain pre-consumer polyethylene waste subject to conditions; the 2025 Amendment Rules (in force 1 April 2026) added a new Chapter VIII on EPR for scrap of non-ferrous metals (aluminium, copper, zinc and alloys), with recycling targets rising from 10% in 2026–27 towards 75% by 2032–33, EPR certificates, a CPCB portal and environmental compensation for non-compliance.

Back to topic map ↑

4.6Other waste and chemical safety regimes#

In brief

Instrument Key points Manufacture, Storage and Import of Hazardous Chemical Rules 1989 Regulate major accident hazard installations; require safety reports, on-site…

Instrument Key points
Manufacture, Storage and Import of Hazardous Chemical Rules 1989 Regulate major accident hazard installations; require safety reports, on-site emergency plans
Chemical Accidents (Emergency Planning, Preparedness and Response) Rules 1996 Crisis groups at central, State, district and local levels
Bio-Medical Waste Management Rules 2016 Segregation in colour-coded bags (yellow, red, white, blue); duty of the occupier; authorisation
Solid Waste Management Rules 2016 Source segregation; local body responsibilities; bulk generator duties (check if replaced by newer rules)
Plastic Waste Management Rules 2016 (amended 2021–2022) EPR for producers, importers and brand owners; ban on identified single-use plastic items from 1 July 2022
E-Waste (Management) Rules 2022 EPR with certificates; refurbishers and recyclers registered with CPCB; in force from 1 April 2023
Battery Waste Management Rules 2022 EPR for batteries; collection and recycling targets
Construction and Demolition Waste Management Rules 2016 Duties of large generators and local authorities
Public Liability Insurance Act 1991 No-fault liability and insurance for hazardous substances
Factories Act 1948, Chapter IVA Hazardous processes; site appraisal committees; worker safety
Disaster Management Act 2005 NDMA, SDMAs and district authorities for chemical and industrial disasters
Recycling of Ships Act 2019 Hazardous materials inventory for ship recycling (Alang)

Back to topic map ↑

4.7Cases on hazardous waste and pollution#

In brief

Bhopal Gas Leak Disaster (1984) and the litigation that followed ( Union Carbide Corp. v. Union of India , 1989; Charan Lal Sahu , 1990) led to the EPA, the Public Liability…

  • Bhopal Gas Leak Disaster (1984) and the litigation that followed (Union Carbide Corp. v. Union of India, 1989; Charan Lal Sahu, 1990) led to the EPA, the Public Liability Insurance Act and the Chapter IVA of the Factories Act.

  • Indian Council for Enviro-Legal Action v. Union of India (1996): Bichhri (Rajasthan) chemical sludge from an illegal plant; the Court applied polluter pays and absolute liability and directed remediation costs.

  • Research Foundation for Science, Technology and Natural Resource Policy v. Union of India (2005, 2007): the Supreme Court dealt with the import and disposal of toxic waste and with an asbestos-laden vessel (the Blue Lady), in the light of the Basel Convention, and ordered a monitoring committee.

  • B.L. Wadehra v. Union of India (1996): municipal solid waste in Delhi; the Court directed the municipal bodies to discharge their duties.

  • M.C. Mehta (Oleum Gas Leak) (1986/87): absolute liability for hazardous industries.

Back to topic map ↑

★Memory Capsule: Environmental Impact Assessment and Control of Hazardous Waste in India

Memorise

  • EIA Notification 1994 → 2006; Category A = Centre (EAC, MoEFCC), Category B = State (SEAC, SEIAA).
  • Four steps: Screening, Scoping, Public consultation, Appraisal.
  • Hazardous waste rules: 1989 → 2008 → 2016; 90-day storage limit; no import of hazardous waste for disposal.

Test yourself on Environmental Impact Assessment and Control of Hazardous Waste in India

Practise with free MCQs and answer keys, then return here to fix what you got wrong.